Archivio per: Timetable

Timetable 11 Jul 2025
Completion of all works

Hydrogeological, geomorphological, and archaeological studies aimed at safeguarding Venice and its lagoon Completion of works on the first and second wharves of the North Canal …

READ MORE  
Timetable 29 Mar 2022
Activity year 2026

Award of contract and start of work on the new sediment placement site Award of contract and start of maintenance work on the Vittorio Emanuele …

READ MORE  
Timetable 29 Mar 2022
Activity year 2025

Environmental Impact Assessment (EIA) and approval of the new sediment site Environmental Impact Assessment (EIA) and approval of the Vittorio Emanuele Canal maintenance Environmental Impact …

READ MORE  
Timetable 29 Mar 2022
Activity year 2024

Award of maintenance project for the Malamocco-Marghera Canal Award of final/executive project and environmental impact study for the first and second landing wharves of the …

READ MORE  
Timetable 29 Mar 2022
Activity year 2023

Award of project for maintenance for the Vittorio Emanuele Canal Award of design contract for the new sediment site Completion of feasibility design for the …

READ MORE  
Timetable 29 Mar 2022
Activity year 2022

Completion of first mooring  upgrade, Liguria Quay Completion of second mooring upgrade, Lombardy Quay An additional mooring is operational in Chioggia Conclusion of the nautical …